Things I have tried
Obsidian automatically added a completion:: metadata to a task that has been marked as completed.
how do I hide this metadata display?
Obsidian automatically added a completion:: metadata to a task that has been marked as completed.
how do I hide this metadata display?
This is coming from a plugin. Do you have any task related plugins enabled? Check their settings.
I only have the Dataview, Calendar and Natural Language Dates plugins installed
is it one of them?
I’m not sure, but you should check the settings of them.
you are correct - it can be toggled via the the Natural Language Dates plugin settings
thx!
This topic was automatically closed 24 hours after the last reply. New replies are no longer allowed.